VA says it tried to fire executive for hospital cost overrun

By: DAN ELLIOTT, Associated Press
June 15, 2016 Updated: June 16, 2016 at 6:12 am
0
photo - AURORA, CO - JULY 01: U.S. Deputy Secretary of Veterans Affairs Sloan Gibson visited the construction site of the VA hospital at Fitzsimmons medical campus to discuss the state of the project. (Photo by AAron Ontiveroz/The Denver Post)
AURORA, CO - JULY 01: U.S. Deputy Secretary of Veterans Affairs Sloan Gibson visited the construction site of the VA hospital at Fitzsimmons medical campus to discuss the state of the project. (Photo by AAron Ontiveroz/The Denver Post) 

AURORA — The Veterans Affairs Department was about to fire one executive because of massive cost overruns at a VA hospital outside Denver, and another was under investigation, but both retired before the department could take an action, Deputy VA Secretary Sloan Gibson said Wednesday.

It was the VA's most detailed public explanation to date about attempts to discipline high-ranking officials over problems that caused the new hospital's price to nearly triple to $1.7 billion. 

Congress has repeatedly demanded that the VA fire the executives responsible for the cost overruns, but to date no one has been dismissed. The VA says everyone who was to blame has left the department.

Gibson identified the two executives who retired only by title, the head of the office of acquisition, construction and logistics and a senior VA attorney. He didn't say which was about to be fired.

Glenn Haggstrom, who held the acquisition and construction job, retired in March 2015, one day after he was interviewed under oath as part of an internal investigation. He didn't immediately return a phone message Wednesday.

Phillipa Anderson, an assistant general counsel in the VA's contract office, retired in June 2015. She said Wednesday she had no knowledge about whether she had been under investigation over the hospital project, and said her retirement wasn't related to the hospital. She declined further comment.

Gibson, speaking at a news conference at the hospital construction site in suburban Aurora, said the VA would not publicly release the results of its internal investigation.

Internal reviews go on all the time, and disclosing this one would make it difficult to conduct them in the future, he said.

"You end up chilling the whole investigative process," he said.

The VA has shown the report to members of congressional committees that oversee the department, Gibson said.

A second investigation by the VA's inspector general is still underway and will be made public when it's complete, he said. It's not clear when that will be.

Investigators blamed the overruns on multiple design changes and a decision by VA officials to use a complicated contract process they didn't fully understand.

"We got a lot of things wrong," Gibson said Wednesday.

The 184-bed hospital is 70 percent complete and construction is expected to be done in January 2018. It will replace an aging, overcrowded facility still in use in Denver.

Gibson said the hospital would be opened in phases but declined to give specifics, saying he wanted to make sure everything was in place before committing to dates.

Register to the Colorado Springs Gazette
Incognito Mode Your browser is in Incognito mode

You vanished!

We welcome you to read all of our stories by signing into your account. If you don't have a subscription, please subscribe today for daily award winning journalism.

Register to the Colorado Springs Gazette
Subscribe to the Colorado Springs Gazette

It appears that you value local journalism. Thank you.

Subscribe today for unlimited digital access with 50% fewer ads for a faster browsing experience.

Already a Subscriber? LOGIN HERE

Wake up with today's top stories in your inbox

Wake up with today's top stories in your inbox

or
Already a print subscriber?
Already a digital subscriber?
 
This is your last FREE article for the month
This is your last FREE article for the month

Subscribe now and enjoy Unlimited Digital Access to Gazette.com

Only 99 cents for Unlimited Digital Access for 1 month
Then $2.31/week, billed monthly, cancel anytime
Already a print subscriber?
Already a digital subscriber?

 
You have reached your article limit for the month
You have reached your article limit for the month

We hope that you've enjoyed your complimentary access to Gazette.com

Only 99 cents for Unlimited Digital Access for 1 month
Then $2.31/week, billed monthly, cancel anytime
Already a print subscriber?
Already a digital subscriber?
 

Exclusive Subscriber Content

You read The Gazette because you care about your community and the local stories you can't find anywhere else.

Only 99 cents for Unlimited Digital Access for 1 month
Then $2.31/week, billed monthly, cancel anytime
Already a print subscriber? Get Access | Already a digital subscriber? Log In
 
articles remaining
×
Thank you for your interest in local journalism.
Gain unlimited access, 50% fewer ads and a faster browsing experience.