Latest: Regulator won't stop work on Atlantic Coast Pipeline

By: Associated Press
May 16, 2018 Updated: May 16, 2018 at 5:10 pm
0

RICHMOND, Va. (AP) — The Latest on a court order involving the Atlantic Coast Pipeline (all times local):

6 p.m.

Federal regulators are not immediately stopping work on the Atlantic Coast Pipeline, even though a federal appeals court invalidated a key permit for the project.

Environmental groups suing over the permit say Tuesday's court order means construction or any associated activity on the multistate pipeline must stop.

Instead, an official with the Federal Energy Regulatory Commission issued a letter Wednesday directing the pipeline to simply file documentation within five days explaining how it will avoid harming threatened or endangered species. The letter notes that developers informed the commission they will not proceed with construction in areas where such sensitive wildlife might be affected.

D.J. Gerken is an attorney with the Southern Environmental Law Center. He says the commission staff appears to be "skipping lightly" over the requirement that a valid permit be in place.

Gerken says it's too soon to comment on next steps.

___

12:30 p.m.

Environmental groups and the lead developer of the Atlantic Coast Pipeline are at odds over what happens now that a federal appeals court has vacated a key permit for the multistate project.

The key developer and the environmental groups that sued disagree over whether work can continue on the natural gas pipeline.

Environmental groups say construction and any associated activity must stop, now that the permit dealing with threatened and endangered species has been invalidated.

But a Dominion Energy spokeswoman says the project "will move forward with construction as scheduled."

A spokeswoman for the federal commission with the lead in pipeline oversight declined to give an immediate comment on the issue.

The approximately $6.5 billion, 600-mile pipeline is designed to start in West Virginia and cross Virginia and North Carolina.

Register to the Colorado Springs Gazette
Incognito Mode Your browser is in Incognito mode

You vanished!

We welcome you to read all of our stories by signing into your account. If you don't have a subscription, please subscribe today for daily award winning journalism.

Register to the Colorado Springs Gazette
Subscribe to the Colorado Springs Gazette

It appears that you value local journalism. Thank you.

Subscribe today for unlimited digital access with 50% fewer ads for a faster browsing experience.

Already a Subscriber? LOGIN HERE

Wake up with today's top stories in your inbox

Wake up with today's top stories in your inbox

or
Already a print subscriber?
Already a digital subscriber?
 
This is your last FREE article for the month
This is your last FREE article for the month

Subscribe now and enjoy Unlimited Digital Access to Gazette.com

Only 99 cents for Unlimited Digital Access for 1 month
Then $2.31/week, billed monthly, cancel anytime
Already a print subscriber?
Already a digital subscriber?

 
You have reached your article limit for the month
You have reached your article limit for the month

We hope that you've enjoyed your complimentary access to Gazette.com

Only 99 cents for Unlimited Digital Access for 1 month
Then $2.31/week, billed monthly, cancel anytime
Already a print subscriber?
Already a digital subscriber?
 

Exclusive Subscriber Content

You read The Gazette because you care about your community and the local stories you can't find anywhere else.

Only 99 cents for Unlimited Digital Access for 1 month
Then $2.31/week, billed monthly, cancel anytime
Already a print subscriber? Get Access | Already a digital subscriber? Log In
 
articles remaining
×
Thank you for your interest in local journalism.
Gain unlimited access, 50% fewer ads and a faster browsing experience.